Revision as of 12:26, 11 May 2017
Contents
Important Machine Operations and Procedures
Powering on/Shutting down Sequence
- The sequence in which the machine/hardware and software are turned on and off is very important. Please follow the instructions as shown here:
Operating the Gates
- The operation of the gates, whether front round, front square, center round or center square, will be conducted on an as needed basis. The movement and adjustment of these gates will not be necessary for every tube/pipe loaded into the Dragon machine. Adjust the gates only when loading a different OD material than the material that was used beforehand.